Week of October 5

10-05-2026Facilities Master Planning Committee Update
  • Exterior sheathing and window blocking for Adoration Chapel and addition
  • If last set of doors arrive, drywall and doorways to be completed in both school and church basements
  • Prime and first coat of paint in church basement